M/HQ Group · Stage 2 · Appendix D

Project plan

Thirty weeks from a 3 August 2026 start to the end-February 2027 close, in three gated releases. Scope flexes; the close does not.

1The shape

The plan works backwards from the close date. The end date was moved from 31 December 2026 to end February 2027 at the 15 July planning session, to take risk out of the schedule: the same work is spread over more weeks, the Group's reduced bandwidth through 1 October is accounted for, and the December holidays are built into the plan.

3 Aug26 Feb R1 · Quick wins R2 · Core R3 · Automation + AI checkpoint 18 Sep R1 gate 30 Oct R2 gate 29 Jan close 26 Feb

2The three gated releases

ReleaseWindowWhat lands, and the gate
R1 · Quick winsAug to 30 Oct 2026Early, selection-independent automation where Stage 1 evidenced the load. A working checkpoint on 18 September; the payment gate on 30 October, after the bandwidth constraint lifts.
R2 · Coreto 29 Jan 2027The owned master record live and reconciled, the capture and ingestion layer live, the selected spokes configured and integrated, UAT signed off.
R3 · Automation, AI and steady stateto 26 Feb 2027The workflow and AI layer, fiduciary review, the annual accounting build, adoption complete, training delivered, and the steady-state handover. Stage 2 closes.

3Deliverables and dates

#DeliverableDue
1Systems selected across the four categories; signed target architecture, data model and tenancy design28 Aug 2026
2Baseline measurement pack (pre-implementation)28 Aug 2026
3Enablement launched: company-wide introduction and foundation training assigned Group-wide, completion trackedAug 2026
4Release 1: quick wins live (checkpoint 18 Sep)30 Oct 2026
5Group master record live, migrated and reconciled11 Dec 2026
6Capture and ingestion layer live15 Jan 2027
7Selected spokes configured and integrated; UAT signed off (Release 2)29 Jan 2027
8Workflow and AI layer live; assistant rolled out with usage and governance policy12 Feb 2027
9Fiduciary review workflow and drafting live12 Feb 2027
10Annual accounting build live on the record (incl. FTA-compliant VAT/CT output)19 Feb 2027
11Adoption programme complete19 Feb 2027
12Training and education programme delivered26 Feb 2027
13Steady-state operating model and handover pack (Release 3, close)26 Feb 2027
14Post-implementation measurement report (against the WS0 baseline)26 Mar 2027
Keeping the date

Three gated releases absorb change without moving the close: if scope grows, it is reprioritised within a release rather than pushed past February. The 1 October bandwidth constraint is planned in, with the heavier Group-side work sitting after it.